We are still progressing, but a couple of unexpected obstacles have had to be dealt with. Alignment of the inlet pipe with the turbine was not good enough and has required some re-modelling and re-alignment, this is in hand. The major delay however relates to our generator which was damaged in transit; a new generator is being supplied but will not be available until late June.